The project will adopt the same approach as used in phase 2.
A list of laminate products to be tested will be agreed by the project team. A test vehicle with minor modifications to that used in phase 2 (see below) will be used.

Boards will be fabricated under controlled conditions. Laminate suppliers will be consulted to ensure that their recommendations are followed for lamination and processing of their materials.
The completed boards will be preconditioned using a typical high end surface mount reflow cycle peaking at a maximum temperature of 260°C. The boards will be passed through the convection oven a total of 6 times, being visually inspected and allowed to cool to ambient after each cycle.
The boards will be then be submitted to a series of tests as defined below.